As I mentioned in my previous post, defining an appropriate scope is difficult when you are attempting to do iterative development on BI/DW projects. The problems with this are not unique to BI/DW projects, of course. All projects have scope issues. Most of the same scope management techniques that work well on traditional application development projects also work for BI/DW projects. There are two unique aspect of scope for BI/DW projects, though. One is that there is often significant work required “behind the scenes” to deliver even small pieces of visible end user functionality. The other is that there can be significant “hidden” scope in properly cleansing the data and making it useful from a business perspective. This can be challenging because the end users may have a perception that they are not getting very much functionality, particularly in the first several iterations of the project.
What are some of the hidden aspects of BI/DW projects? ETL and data profiling are two of the most common. I consider these hidden because the end users of a BI application rarely are intimately involved in the ETL process development. They may be involved in the data profiling, but often are not involved in the data cleansing that usually accompanies it. These are time-consuming activities that the users only get to appreciate indirectly, so they often don’t put very much value on it.
How can this be addressed? I’ve found that there’s two parts to it. First, you need to do a certain amount of education with the stakeholder on what happens behind the scenes, so that they have a better understanding of the effort that has to be expended. The benefits that they get from this effort need to be explained as well. Telling them that ETL processes are time-consuming to implement isn’t very effective unless you also explain the benefits of well-implemented ETL: cleaner, consistent, conformed data, with appropriate controls to verify that the right data is going into the data warehouse, and the bad data is being excluded.
However, education is not enough by itself. The second part of it is to show them that they can get incremental benefits. Again, as pointed out in the previous article, each iteration should deliver something of value to the users. It’s important to do this from the first iteration on, and to continue to do it consistently. One effective way to determine what would be of value for an iteration is to ask the users to decide on one or two questions that they want to be able to answer. The scope of the iteration becomes delivering the information that allows them to answer those questions. But what if the questions are complex, and you don’t feel that they can be addressed in a single iteration? I’ve generally found that if the questions are that complex, you can break them up into smaller questions and negotiate with the stakeholders to deliver them over multiple iterations.
This does require that the development team on the project has an agile mindset, and is focused on meeting the deliverables for the iteration. It also poses a more significant challenge when a project is in an initial phase, and the infrastructure is still being put in place. I’ll discuss this challenge further in my next post.
In conclusion, scope management is important on all projects, not just BI/DW projects. However, perceptions of scope may be more challenging on BI/DW challenges, because of the hidden nature of some of the activities. It’s important to communicate the value of these activities to the project stakeholders, and to demonstrate that you can consistently produce incremental deliverables, while still carrying out these valuable activities.